Poultry · PO-007

Stand-off interior draft deflector

Redirect a direct air jet from an existing high vent without closing the vent or reducing it to a tiny slot.

Editorial construction draft. Original digital diagrams; no physical build or load certification. Read dimensions, fit and use limits before making changes. US customary dimensions control; metric values are references.

Before marking and cutting

Use limits

Materials and cuts

PartQtySize to cutMaterial
A Deflector plate128 × 12 × 1/2 in
711.2 × 304.8 × 12.7 mm
Exterior-bond plywood, measured actual thickness. Square ends; remove splinters.
B Stand-off block43 × 1 1/2 × 1 1/2 in
76.2 × 38.1 × 38.1 mm
Untreated sound straight softwood. Square ends; remove splinters.

Hardware and consumables

Tools

Assembly

PO-007 dimensioned assembly
  1. Select an existing high wall vent no larger than 24 × 6 in (609.6 × 152.4 mm) for this example. The 28 × 12 in plate must be above the birds and out of their landing route.
  2. Confirm that a 3 in (76.2 mm) open perimeter gap can remain around the plate; do not install inside an enclosure where side airflow paths would be blocked by shelves or insulation.
  3. Cut A to 28 × 12 in from actual 1/2 in plywood; sand every edge and fully cure any compatible edge finish before installation.
  4. Cut four B blocks to 3 in long from actual 1 1/2 in square stock. Mark the center of both end faces.
  5. Place each B at a plate corner: left blocks x = 0–1 1/2 in, right blocks x = 26 1/2–28 in; bottom/top blocks occupy the corresponding 1 1/2 in strips.
  6. Clamp blocks to A and drill a 9/32 in (7.1 mm) clearance hole through each block and its plate position on the same axis, using a backing board to reduce breakout.
PO-007 dimensioned parts or elevation
  1. With the actual wall exposed and inspected, transfer the four hole centers. This example assumes accessible sound 3/4 in wood backing; stop if the wall is hollow, structural alterations are needed, or the reverse face is inaccessible.
  2. Fit four 1/4 × 5 in through-bolts from the room side through washer, A, B and the 3/4 in backing. Add rear washers and locking nuts; trim/cap any remaining point on the reverse side.
  3. Tighten gradually until the spacers seat without crushing the plate. Do not pull an irregular wall flat by bending A.
  4. Measure the stand-off at all four corners: 3 in clear from wall face to back of A. Ensure no bedding, curtain or loose foam can migrate into that gap.
  5. Observe moisture and drafts under actual conditions; a redirected jet is not evidence of adequate air exchange. Remove or redesign the deflector if condensation, odor or poor air quality develops.
  6. Remove the four nuts for periodic cleaning, with birds excluded. Return the same spacers to retain the full opening and dry all components before reinstalling.

Checks

Cleaning and maintenance

Primary context